Harvest Barn

Construction of this barn began May 6th and the concrete was poured 7 days later on May 13th.

101_86001

101_86082

The framework began next and the trusses were put on the buildings on June 17th.

101_87703

101_87744

Framework was continued on the trusses and the steel roof was added June 30th.

102_42015

102_42036

As the roof was going on electricians began the wiring in the building.

102_42097

The wiring has been completed and the siding to the barn has begun to be added.

102_4226

102_4227

102_4224

The siding is finally done and it has been stained a beautiful barn red.

102_4261

102_4268

Work on this building has been stopped to continue construction on the Admissions Barn. The next step is to complete the Admissions Barn up to the same point as the Harvest Barn and then move into the insides to begin the interior.

Check back later for more updates.